“My launch slipped a week and the team is deflated. What do I do?”
First, what's the denominator? One week late on a build that ran how many? Say both numbers out loud, because a slip with no scale feels bigger than it is. Then break the week out by workstream: review, a dependency, scope that grew. One cause usually owns most of it, and a named cause reads like a fix instead of a verdict on the team.
Show them one plain chart, planned versus actual per workstream, with the finding as the title. Then check noise versus pattern: did the last few launches slip the same way? Next query: what that one workstream waited on.